Updated November 23, 2026
Direct Answer
The cost to build a house in Ontario runs $400 to $750+ per square foot in Burlington and $500 to $1,130 in the Greater Toronto Area (GTA), before land, development charges, harmonized sales tax (HST) and soft costs. Enhanced HST relief needs construction to start by March 31, 2027, with home and land under $1.85M.
TL;DR
- Burlington custom homes run $400 to $750 and up per square foot; GTA custom builds run $500 to $1,130.
- On your own lot, enhanced HST relief needs construction to start between April 1, 2026 and March 31, 2027.
- The HST value test includes land: up to $130,000 back at $1.5M or less, up to $24,000 at $1.85M and above.
- Development charges run from about $75,000 in Kitchener and Waterloo to over $170,000 in Markham.
- A Halton teardown gets the Regional share credited if the new permit comes within five years of demolition.
- Add 5 to 8% for soft costs and 12 to 15% for contingency.
One liner: Price the lot, the charges and your HST start date at the same time as the build.
Key Numbers
| Stat | What it measures | Source |
|---|---|---|
| $400 to $550 per sq ft | Mid-range custom build rate in Burlington | Catlin, 2026 |
| $500 to $1,130 per sq ft | Custom-built single family rate in the GTA | Altus Group, January 2026 |
| $150 to $275 per sq ft | Production home rate in the GTA, unfinished basement | Altus Group, January 2026 |
| 13% | HST on a new home in Ontario | Canada Revenue Agency, 2026 |
| $130,000 | Most enhanced HST relief available, provincial and federal portions together | Government of Ontario, 2026 |
| Under $1.85M | Value of home and land at completion for any enhanced HST relief | Canada Revenue Agency, 2026 |
| $114,376 | Development charges on a new single detached home in Burlington | Residential Construction Council of Ontario (RESCON), July 2026 |
| $79,880.67 | Halton Region’s share for a single detached home in the built boundary | Halton Region, April 2026 |
| 5 years | Window between demolition permit and new building permit for Halton’s credit | Halton Region, 2022 |
| 5 to 8% | Soft costs on top of a Burlington build contract | Catlin, 2026 |
How the Cost to Build a House in Ontario Stacks Up
In short: Build rates come first, then charges, HST and soft costs on top, with one HST date to watch.
Ask three people about the cost to build a house in Ontario and you’ll hear three different per square foot numbers. Each one can be right and still leave a six-figure gap in your budget. The build rate is only the first layer. Development charges, HST and soft costs sit on top. For anyone building in 2027, one date decides how much of that HST comes back.
Here’s how the layers stack on a 3,500 square foot home in Burlington:
- Build: $1.4M to $1.93M at $400 to $550 per square foot
- Development charges: about $114,000 on a new lot, or a credit for the house you replace on a teardown, if the new building permit comes within five years of the demolition permit
- HST: 13% on the build
- Soft costs: 5 to 8% on top of the contract
- Contingency: 12 to 15%
Land is separate again.
Location changes the fixed charges most visibly. Development charges alone run from about $75,000 per home in Kitchener and Waterloo to more than $170,000 in Markham. That’s a gap of about $97,000 before anyone pours a footing.
Building in Halton? Start with what a Burlington custom home costs, then use the figures below to compare the rest of Ontario.
HST on a New Custom Home: The Construction Start Date That Decides Your Rebate
In short: On your own lot, the HST relief depends on when construction starts and what the home and land are worth.
On a custom home built on land you already own, the enhanced HST relief turns on when construction starts, not when you sign a contract. Work has to begin between April 1, 2026 and March 31, 2027, and the home has to be substantially complete by December 31, 2029.
That’s because a home you build, or hire someone to build, on your own lot counts as owner-built for HST purposes. Signing with a builder in March 2027 doesn’t qualify the home if work on site begins in May.
The second test is value. The Canada Revenue Agency (CRA) uses the home’s fair market value at substantial completion. That value includes the land. Here’s how the relief steps down:
| Value of home and land at completion | Provincial 8% portion | Federal 5% portion |
|---|---|---|
| Up to $1M | Full relief, up to $80,000 | Full relief, up to $50,000 |
| Over $1M to $1.5M | Flat $80,000 | Flat $50,000 |
| Over $1.5M to under $1.85M | Partial relief | Partial relief |
| $1.85M and above | Standard Ontario rebate only, up to $24,000 | None |
The provincial portion is the Ontario Enhanced New Housing Rebate (ENHR), which the CRA administers. The federal portion comes back through the Ontario New Home Affordability Payment (ONHAP), which Ontario pays. The ONHAP is reduced by any federal rebate you claim, including the first-time home buyers’ rebate. Relief can’t exceed the HST you actually paid. Owner-built claims use Forms GST191 and RC7191-ON.
Picture a home worth $1.4M with its lot at completion. If construction starts in March 2027, the owner can claim up to $130,000 in relief. If the same home starts in April 2027, the enhanced relief is gone. The standard Ontario rebate tops out at $24,000. That’s a $106,000 swing from one month on the calendar.
The CRA’s rebate guide doesn’t define the start date for an owner-built home. Keep dated proof of when work begins on site, and check your own case with the CRA or a tax professional.
A March 2027 start needs design, drawings and permits done in time. Catlin reviews the site and zoning, prepares permit drawings and manages approvals as part of custom home building in Burlington.
Custom Home Cost per Square Foot: Ontario Ranges by Region
In short: Custom and production rates differ by hundreds of dollars per square foot, so check which one you’re reading.
Custom home cost per square foot in Ontario changes with the kind of home and with what the rate leaves out. Altus Group publishes yearly cost ranges based on real projects. Its 2026 guide splits production homes from custom-built homes, and the gap between them is wide.
| Region | Home type | Cost per sq ft | Source |
|---|---|---|---|
| Burlington | Mid-range custom | $400 to $550 | Catlin |
| Burlington | Premium custom | $550 to $750 | Catlin |
| Burlington | Luxury custom | $750 and up | Catlin |
| GTA | Custom-built single family | $500 to $1,130 | Altus Group |
| GTA | Production home, unfinished basement | $150 to $275 | Altus Group |
| Ottawa | Custom-built single family | $500 to $1,000 | Altus Group |
| Ottawa | Production home, unfinished basement | $160 to $230 | Altus Group |
Here’s what that gap looks like on a 3,000 square foot home in the GTA. At production rates, the build comes to $450,000 to $825,000. At the low end of the custom range, it’s $1.5M. When you see one “average” cost per square foot to build a house in Ontario, check which kind of home it describes.
Check what it leaves out, too. The Altus rates are as at January 31, 2026, and they exclude HST, land, soft costs and site development. For wood-framed homes, they also leave unfinished basement and garage space out of the square footage.
Altus doesn’t publish separate rates for Hamilton or Halton. For Halton, use Catlin’s Burlington figures, which run from mid-range to luxury. Catlin’s Burlington pricing breakdown covers what drives each tier, from lot conditions to finishes.
Development Charges by Region, and the Teardown Credit in Halton
In short: Charges vary by tens of thousands across Ontario, and a Halton teardown gets the Regional share credited.
Development charges are one-time fees that pay for the roads, pipes and services new homes use. For a single detached house, the development charges Halton new home buyers face top $114,000. Here’s what a single detached home pays in mid-2026, from the Residential Construction Council of Ontario (RESCON) and the City of Hamilton:
| Municipality | Charges per single detached home | Source |
|---|---|---|
| Oakville | $151,010 | RESCON |
| Toronto | $141,739 | RESCON |
| Mississauga | $138,025 | RESCON |
| Milton | $123,192 | RESCON |
| Burlington | $114,376 | RESCON |
| Hamilton | $84,881 to $106,030, before partial exemptions | City of Hamilton |
| Kitchener and Waterloo | $74,872 | RESCON |
RESCON’s figures combine municipal, regional and education charges. They leave out discounts and area-specific charges. Hamilton’s range covers City and education charges by area, before its 20% and 4% partial exemptions.
In Burlington, Halton Region’s share is the biggest piece: $79,880.67 per single detached home inside the built boundary. Urban lots also carry a $9,500 Front-ending Recovery Payment (FERP).
North Burlington’s rural lots work differently. A rural lot that isn’t on municipal water and wastewater pays a lower Regional charge of $41,368.50, plus the $1,174.95 roads portion of the FERP. The trade-off is a private well and septic system in your build budget.
A teardown changes the math. When you demolish a house and build a new one on the same lot, Halton Region credits each demolished dwelling unit against the new charges. The building permit for the new home has to be issued within five years of the demolition permit. The credit can’t exceed the charges owed, and a building that was exempt earns none. Hamilton applies a five-year credit to City and education charges, and Oakville does the same for Town charges.
Picture two Burlington buyers with the same plans. One tears down a 1960s bungalow and gets the new permit within a year. The other builds on a lot freshly severed from a neighbour’s yard. The first buyer’s Regional share is credited against the bungalow it replaces. The second pays the full Regional charge. Check the City and school board shares for your own lot, since each sets its own terms.
Bill 17, the Protect Ontario by Building Faster and Smarter Act, 2025, also changed the timing. The municipal and regional share for a non-rental home can now be paid at occupancy, not at permit. Education charges and the FERP are still collected before the building permit.
Soft Costs of Building a House
In short: Plan 5 to 8% on top of the build for soft costs, plus a contingency.
The soft costs of building a house are the bills that come with the project but aren’t part of the structure. Per square foot rates leave them out. Altus Group’s ranges, for example, exclude architectural and engineering fees, permits, and financing.
For a custom home in Burlington, Catlin’s guidance is to add 5 to 8% on top of the build contract for these items:
- Interest on your construction loan
- Property taxes while the house is built
- Builder’s insurance
- Temporary housing if you’re rebuilding where you live
- Storage for your belongings
- Final landscaping
On a $1.6M build contract, that’s $80,000 to $128,000.
Some soft costs may already sit inside your contract. Catlin’s custom home service covers design, permit drawings and approvals. In Catlin’s budget split, permits and design take 4 to 7% of the build cost, and contingency and project management take 5 to 10%. Ask each builder which items their price includes, so nothing gets counted twice. For local permit fees, see our guide to building permit cost in Burlington.
Then set a contingency. Catlin recommends adding 12 to 15% to your per square foot estimate. Development charges and HST sit outside all of this, as covered above.
A Sample 2027 Budget for a Burlington Custom Home
In short: A 3,500 square foot Burlington build runs $1.64M to $2.48M before HST and land.
Here’s how the layers add up for a 3,500 square foot mid-range home in Burlington. The low end of each range uses the lower rate and percentage, and the high end uses the higher ones. Land is left out.
| Budget line | Teardown on a lot you own | New lot |
|---|---|---|
| Build at $400 to $550 per sq ft | $1.4M to $1.93M | $1.4M to $1.93M |
| Soft costs at 5 to 8% | $70,000 to $154,000 | $70,000 to $154,000 |
| Contingency at 12 to 15% | $168,000 to $289,000 | $168,000 to $289,000 |
| Development charges | Regional share credited if the new permit comes within 5 years of demolition | About $114,000 |
| Subtotal before HST and land | $1.64M to $2.37M, plus any City or school board charges not credited | $1.75M to $2.48M |
| HST at 13% on the build, if your quote is before tax | $182,000 to $250,000 | $182,000 to $250,000 |
| HST relief | Up to $130,000 if work starts by March 31, 2027 and the home with land is worth $1.5M or less; partial up to $1.85M; otherwise up to $24,000 | Same rules |
Two lines can change by six figures before you pick a single finish. The development charge line can swing by about $114,000 depending on whether you’re replacing a house. The HST relief line can swing by $106,000 depending on your start date and the home’s value with land.
Timing matters at both ends. Catlin puts the full timeline at 14 to 24 months from pre-construction to move-in. For the enhanced relief, the home also has to be substantially complete by December 31, 2029.
Your own numbers will depend on the lot, the design and the finishes you choose. Use this table as a checklist of lines to price. Then replace each range with real quotes.
Planning a Custom Home in Burlington, Oakville or Hamilton
In short: Price your lot, charges and start date early with a design-build team.
The cheapest budget surprise is the one you find before you sign. Your lot, the charges and your start date all shape the final number. Price them early.
Catlin is a design-build firm based in Burlington. It builds custom homes, whole-home renovations and additions across Burlington, Oakville, Hamilton and nearby communities. One team handles design, permits and construction.
Each city has its own page. As a custom home builder in Oakville, Catlin plans around zoning, grading, tree protection and lot conditions. As a custom home builder in Hamilton, it runs planning and construction with one coordinated team.
Call 289-427-1092 or visit the office at 919 Fraser Drive, Unit 9, in Burlington. Bring your lot address and a rough size. Then ask how a 2027 start would fit your plans.
Frequently Asked Questions
In short: Quick answers on per square foot rates, HST, development charges, soft costs and timelines.
How much does it cost to build a house in Ontario per square foot?
A custom home in Burlington runs $400 to $550 per square foot at mid-range, $550 to $750 at premium, and $750 and up for luxury. In the GTA, custom-built homes run $500 to $1,130. Those rates leave out land, development charges, HST and soft costs.
Is there HST on a new custom home in Ontario?
Yes. HST is 13%. On a custom home on your own land, enhanced relief applies only if construction starts between April 1, 2026 and March 31, 2027. The home’s value at completion, land included, decides how much relief you get. At $1.85M and above, only the standard Ontario rebate of up to $24,000 applies.
Do I pay development charges if I tear down and rebuild in Halton?
Halton Region credits the house you demolish against the new home’s charges, if the new building permit is issued within five years of the demolition permit. The City and school boards set their own terms, so confirm those shares for your lot. On a new lot in Burlington, total charges are about $114,000.
What are the soft costs of building a house?
Soft costs cover construction loan interest, property taxes during the build, builder’s insurance, temporary housing, storage and final landscaping. For a custom home in Burlington, Catlin suggests adding 5 to 8% on top of the build contract for these items, plus a contingency of 12 to 15%.
How long does it take to build a custom home in Burlington?
Catlin puts the timeline at 14 to 24 months from pre-construction to move-in. If you’re counting on the enhanced HST relief, the home also has to be substantially complete by December 31, 2029. Plan the design and permit stage with both dates in mind.
Definition Bank
| Term | Meaning |
|---|---|
| Development charges | One-time municipal fees on new homes that pay for growth-related roads, water, sewers and services. |
| Front-ending Recovery Payment (FERP) | A $9,500 Halton Region payment on urban residential lots, collected before the building permit. |
| Built boundary | Halton Region’s area of existing urban development, which has its own development charge schedule. |
| Owner-built home | For HST rebates, a home you build, or hire someone to build, on land you own or lease. |
| Fair market value | What the home and land would sell for in an open market when the home is substantially complete. |
| Substantial completion | The CRA’s term for a home that is generally 90% or more complete and can reasonably be lived in. |
| Ontario Enhanced New Housing Rebate (ENHR) | Temporary relief of up to $80,000 of the 8% provincial portion of HST on a new home. |
| Ontario New Home Affordability Payment (ONHAP) | Ontario’s payment of up to $50,000, equal to the 5% federal portion of HST. |
| Demolition credit | A reduction in development charges for dwelling units demolished on the same lot within the by-law’s time limit. |
| Soft costs | Project costs outside the structure, such as fees, financing, insurance and temporary housing. |
| Contingency | A reserve added to the budget for unknowns. |
| Production home | A home built to a builder’s standard plans, as opposed to a custom design. |
Entity Cards
Ontario Enhanced New Housing Rebate
| Property | Value |
|---|---|
| Administered by | Canada Revenue Agency |
| Maximum | $80,000 |
| Owner-built start window | April 1, 2026 to March 31, 2027 |
| Substantially complete by | December 31, 2029 |
| Value test | Under $1.85M, land included |
| Forms | GST191 and RC7191-ON |
Ontario New Home Affordability Payment
| Property | Value |
|---|---|
| Administered by | Government of Ontario |
| Maximum | $50,000 |
| Tiers | Full to $1M, flat $50,000 from $1M to $1.5M, partial to $1.85M |
| Reduced by | Federal rebates claimed, including the first-time home buyers’ rebate |
Halton Region development charges
| Property | Value |
|---|---|
| By-law | 25-22 |
| Single detached, built boundary | $79,880.67 |
| FERP, urban lots | $9,500 |
| Rural, not on water and wastewater | $41,368.50 plus $1,174.95 roads FERP |
| Demolition credit | Building permit within 5 years of the demolition permit |
| Rates | April 1, 2026 to March 31, 2027 |
Altus Group 2026 Canadian Cost Guide
| Property | Value |
|---|---|
| As at | January 31, 2026 |
| GTA custom-built | $500 to $1,130 per sq ft |
| Ottawa custom-built | $500 to $1,000 per sq ft |
| Excludes | HST, land, soft costs and site development |
Catlin
| Property | Value |
|---|---|
| Type | Design-build firm |
| Office | 919 Fraser Drive, Unit 9, Burlington |
| Services | Custom homes, whole-home renovations and additions |
| Phone | 289-427-1092 |
Sources
- Catlin. What Does It Actually Cost to Build a Custom Home in Burlington? (June 30, 2026)
- Altus Group. 2026 Canadian Cost Guide, construction costs as at January 31, 2026 (released April 23, 2026)
- Canada Revenue Agency. GST/HST Notice 346, Ontario Enhanced New Housing Rebate (August 2026)
- Government of Ontario. The Ontario New Home Affordability Payment (updated September 17, 2026)
- Residential Construction Council of Ontario (RESCON). Residential Development Charges (as of July 1, 2026)
- Halton Region. By-law No. 25-22, Development Charges, section 31 (May 25, 2022)
- Canada Revenue Agency. Guide RC4028, GST/HST New Housing Rebate
- Catlin. Custom Home Building
- City of Hamilton. Development Charges Pamphlet, Rates Effective June 1, 2026 through May 31, 2027 (2026)
- Halton Region. Development Charges (DCs) and Front-ending Recovery Payment (FERP), rates April 1, 2026 to March 31, 2027 (2026)
- Town of Oakville. Development Charges
- City of Burlington. Pipeline to Permit Committee, report on deferring development charges to occupancy under Bill 17 (November 13, 2025)
- Catlin. Custom Home Builder in Burlington
- Catlin. Custom Home Builder in Oakville
- Catlin. Custom Home Builder in Hamilton