Updated November 23, 2026. By Catlin.
Take a 280 m² house, with the garage and unfinished basement left out of the count. Its building permit fee is 280 times $23.18, or $6,490. Add the approvals and development charges, and the permit comes to less than a tenth of the bill. Below, you’ll see how the City sets each Burlington building permit fee, which approvals come first, and how the numbers change for an addition.
Direct Answer
Burlington home building permits cost $23.18 per square metre of new floor area, with a $377 minimum, plus about $3,800 in Pre-Building Approval fees for a new house. Development charges are the bigger bill: well over $100,000 on a new home, most of it due before move-in, and nothing on an addition.
TL;DR
- A Burlington building permit costs $23.18 per m² of new floor area up to 300 m² in total, $29.90 per m² above that, with a $377 minimum.
- Pre-Building Approval comes first: zoning, grading and tree reviews add about $3,800 for a new house and about $1,800 for a small addition.
- An addition that only enlarges your home pays no development charges.
- On a new home, development charges run well over $100,000, and since November 3, 2025 the City and Region portions can wait until the occupancy permit.
- Crossing 75 m² raises an addition’s grading fee from $360 to $1,645, and a minor variance from $1,145 to $6,865.
- Starting work before the permit is issued adds a penalty fee, so get the permit in hand first.
One liner: The permit fee is the small line; development charges and the approvals before the permit decide the budget.
Key Numbers
| Stat | What it measures | Source |
|---|---|---|
| $23.18 per m² | Building permit rate, house or addition up to 300 m² total | City of Burlington, 2026 |
| $29.90 per m² | Building permit rate over 300 m² total | City of Burlington, 2026 |
| $377 | Minimum building permit fee | City of Burlington, 2026 |
| $2,110 | Zoning review, new single detached house | City of Burlington, 2026 |
| $1,645 / $360 | Grading review, new house or addition 75 m² plus / small addition | City of Burlington, 2026 |
| $1,420 | Zoning review, residential addition | City of Burlington, 2026 |
| $79,880.67 | Halton Region development charge, urban single detached | Halton Region, 2026 |
| $9,500 | Halton Region FERP, single detached | Halton Region, 2026 |
| $7,052.25 | Halton District School Board education charge per unit | Halton District School Board, 2026 |
| $1,145 / $6,865 | Minor variance fee, smaller work / new house or addition over 75 m² | City of Burlington, 2026 |
| November 3, 2025 | City and Region development charges deferred to occupancy | Ontario Ministry of Municipal Affairs and Housing, 2025 |
| 10 business days | City review of a complete permit application | City of Burlington, 2026 |
What Burlington Home Building Permits Cost in 2026
In short: City fees run about $10,500 for a typical new house and about $2,700 for a small addition, before development charges.
The table compares a 280 m² new house with a 40 m² addition, using the City’s 2026 rates. The addition is under 75 m², which keeps it in the lower fee tier for grading review.
| Fee | New house, 280 m² | Addition, 40 m² | Stage |
|---|---|---|---|
| Zoning review | $2,110 | $1,420 | Pre-Building Approval |
| Grading review | $1,645 | $360, when grading review applies | Pre-Building Approval |
| Forestry application, if trees are affected | $61.02 | $61.02 | Pre-Building Approval |
| Building permit | $6,490 | $927 | Permit issuance |
| Occupancy permit for a new dwelling unit | $191 | No new unit | Occupancy |
| City fees, before development charges | $10,497 | $2,707 | |
| Development charges | Well over $100,000 | $0 | Mostly before move-in |
Read across the bottom row. The house and the addition are about $7,800 apart in City fees, but the development charges split them by six figures. That one line decides most of the budget for a new home, and it doesn’t change with the size of the house. The next section explains who charges it, when it’s paid, and why an addition skips it. The building permit fee is the only City line that grows with your floor area.
Development Charges: Additions Pay None, New Homes Pay Most Before Move-In
In short: An addition to your existing house pays no development charges. On a new house, most of the charge now waits until the occupancy permit.
On a new house, most development charges are no longer paid when the building permit is issued. Since November 3, 2025, the City and Region portions can wait until the occupancy permit, at the amount set when the permit was issued. You can still pay earlier if you’d rather.
Additions: No Development Charges
Under the City’s by-law, an addition that only enlarges your existing home is fully exempt. It’s one of the exemptions set by Ontario’s Development Charges Act, 1997, so it isn’t a discretionary City break. The $0 in the table holds as long as the addition makes your home bigger and doesn’t create a separate dwelling unit. If you’re planning a home addition in Burlington, that’s the biggest cost gap between adding on and building new.
New Homes: What’s Due at Permit and What Waits
| Charge | Single detached house | When it’s paid |
|---|---|---|
| Halton Region | $79,880.67 | Before first occupancy |
| Halton Region recovery payment (FERP) | $9,500 | At building permit |
| City of Burlington | $21,672 (City schedule, June 1, 2025) | Before occupancy |
| Halton District School Board | $7,052.25 (from June 1, 2026) | At building permit |
| Halton Catholic District School Board | Board’s own schedule | At building permit |
The Region figures are for urban lots. A rural lot in north Burlington pays a Region charge of $41,368.50 instead. Here’s what changed for cash flow. Before November 2025, the whole bill came due before the first shovel. Now the two largest lines land at the end of the build. The catch is the occupancy permit. It’s now required for these homes, and the City won’t issue it until the deferred charges are paid. The City can take up to 10 business days for that occupancy inspection, so book it with the payment ready.
Knockdown Rebuilds: The Demolition Credit
Replacing an older house? The City’s by-law allows a credit when a building is demolished and replaced on the same land, as long as the land held an occupied building. The credit has conditions, so confirm it with the City before the demolition permit is issued. If you’re still deciding whether to renovate or rebuild, factor the credit into that comparison.
How the City Calculates Burlington Building Permit Fees
In short: The fee is a rate per square metre times your new floor area, and the rate goes up once a house passes 300 m².
Burlington building permit fees follow one formula: a service rate for the type of work, times the floor area of that work in square metres, rounded to the nearest dollar. Every permit pays at least $377. The fee covers the City’s plan review and its site inspections during the build.
Floor area is measured to the outer face of the exterior walls. Habitable attics and lofts count. Residential garages don’t, and neither does the unfinished basement of a single detached house.
| Work | Rate |
|---|---|
| House, semi, townhouse or addition, up to 300 m² total | $23.18 per m² |
| Same work, over 300 m² total | $29.90 per m² |
| Interior alterations | $8.25 per m² |
| Garage, deck, carport or covered patio, as a separate item | $377 flat |
| Basement walkout or exterior stairs | $377 flat |
| Demolition, up to 600 m² | $377 flat |
The 300 m² line is where size starts to cost more than you’d expect. A 300 m² house pays 300 times $23.18, or $6,954. A 320 m² house is in the over-300 class, so it pays 320 times $29.90, or $9,568. That’s $2,614 more for 20 m². If your plans land near 300 m², ask your designer to show you the count before the drawings are final.
Once the application is complete, the City reviews it within 10 business days and either issues the permit or sends a list of items to fix.
Pre-Building Approval: Burlington’s Fees Before the Permit
In short: Burlington checks zoning, grading and trees before it’ll accept a building permit application, and each review has its own fee.
The pre-building approval Burlington uses for houses and additions covers three reviews, all handled by the City’s Community Planning department before the building permit stage. Here’s the order, ending with the permit itself:
- Zoning Clearance Certificate. This confirms your plans meet the zoning by-law, and you need it before you can apply for a building permit.
- Grading and Drainage Clearance Certificate. The City won’t issue a building permit on a residential lot of ten or fewer units without one. The grading plan needs a Professional Engineer’s or Ontario Land Surveyor’s stamp.
- Forestry review. If the work affects trees, the tree review sits inside the same application.
- Building permit application. Once the clearances are in hand, the permit application goes to the Building department.
Two costs here don’t show up in the fee table. Grading securities are paid before the certificate is issued, and you get them back only after a final inspection shows the work matches the approved plan. And from the third zoning submission onward, each revision costs $680. A complete first package is the cheapest package. That’s one reason design-build teams line up drawings, surveys and grading plans before anything is filed, as the design-build process for a custom home shows.
Permit Fees for an Addition in Burlington
In short: Additions pay the same per square metre rate as a new house, but crossing 75 m² raises the grading fee and, if you need one, the minor variance fee.
Permit fees for an addition in Burlington start with the same $23.18 per m² as a new house, counted on the new floor area. Existing rooms you renovate as part of the job add $8.25 per m². The zoning review is a flat $1,420 for any residential addition, and as covered above, there are no development charges.
Size matters at one line: 75 m².
| Fee | Under 75 m² | 75 m² or more |
|---|---|---|
| Zoning review | $1,420 | $1,420 |
| Grading review | $360 | $1,645 |
| Minor variance, if needed | $1,145 | $6,865 |
| Building permit | $23.18 per m² | $23.18 per m² |
Here’s how that plays out. A 70 m² addition pays $3,403 in City fees: $1,420 for zoning, $360 for grading and $1,623 for the permit. An 80 m² addition pays $4,919, mostly because grading jumps to $1,645. If both designs need a minor variance, the gap grows from $1,516 to $7,236. So if your plans sit close to 75 m², it’s worth asking whether the design still works on the smaller side of the line. City fees are a small share of an addition budget, though. Construction drives the total, and the nine factors behind a Burlington addition budget cover that side.
When You Need a Minor Variance in Burlington
In short: If the zoning review finds your design breaks a zoning rule, the Committee of Adjustment can approve a small exception, for a fee that depends on the project.
You need a minor variance when the zoning review finds your plans outside a rule, such as a setback, a height limit or lot coverage. The minor variance Burlington grants is an approved exception to that rule, decided by the City’s Committee of Adjustment under section 45(1) of Ontario’s Planning Act. Picture a rear addition that reaches 1 m into the required rear yard. That one metre is a variance, and the addition’s size sets which fee you pay.
The Committee weighs whether the change is minor, whether it suits the property, and whether it keeps the general intent of the zoning by-law and the Official Plan. Before any of that, check which rules apply. Burlington has more than one zoning by-law in force, including Residential Zoning By-law 09-2026, effective March 2, 2026, so your limits depend on which one covers your lot.
| Application | City fee |
|---|---|
| Existing house: decks, fences, pools, accessory buildings, additions under 75 m² | $1,145 |
| New detached or semi-detached house, addition over 75 m², additional unit | $6,865 |
| Deferral requested by the applicant | $725 |
Halton Region adds $41.92 when the file is circulated to it, and Conservation Halton may charge its own fee on lots it regulates. A variance is its own application, with public notice and a hearing, so build those weeks into the schedule before zoning clearance can finish.
Fees That Catch Homeowners Off Guard
In short: Starting work before the permit is issued, or asking for a conditional permit, adds fees on top of the regular permit.
Start work before the permit is issued and the City adds a penalty fee. On a permit of $5,000 or less, it’s another 100% of the permit fee. Above that, it’s $5,000 plus 10% of the amount over $5,000. For the 280 m² house from the start of this guide, with its $6,490 permit, starting early adds $5,149.
A conditional permit lets construction begin before every approval is in place. It costs an extra 20% of the full permit fee, or $1,298 on that same house. Both fees are avoidable when the approvals are lined up in order and the permit is in hand before anyone breaks ground.
How Catlin Handles Permits and Approvals
In short: Catlin prepares the permit drawings and manages the submissions and approvals on its custom homes.
Catlin is a Burlington design-build team for custom homes, whole home renovations and home additions, working across Burlington, Hamilton, Ancaster, Oakville, Dundas and Waterdown. For custom home building in Burlington, the team reviews your site and zoning requirements, prepares the permit drawings, and manages the submissions and approvals. Permits and approvals sit as their own stage in Catlin’s process, between design and construction.
The first step is an initial consultation. Bring your lot address and a rough floor area, and the fees in this guide can be priced for your project. Call 289-427-1092, or visit the office at 919 Fraser Dr #9 in Burlington, Monday to Friday, 8am to 5pm.
Frequently Asked Questions
In short: Quick answers on permit cost, development charges for additions and new homes, what counts as floor area, and review time.
How much does a building permit cost in Burlington?
The City charges $23.18 per m² of new floor area for a house or addition up to 300 m² in total, with a $377 minimum. A 280 m² house pays $6,490. Pre-Building Approval fees for zoning, grading and trees are separate and come first.
Do I pay development charges on a home addition in Burlington?
No. An addition that only enlarges your existing home is fully exempt from development charges. The exemption covers making your home bigger, not creating a separate dwelling unit.
When are development charges paid on a new home in Burlington?
The City and Halton Region charges are paid before the occupancy permit is issued, at the amount set when the building permit was issued. The Region’s $9,500 recovery payment and the school board charges are still paid at the building permit stage.
Does the permit fee count my garage or basement?
Not a residential garage, and not the unfinished basement of a single detached house. Floor area is measured to the outer face of the exterior walls, and habitable attics and lofts are included.
How long does Burlington take to review a building permit?
The City reviews a complete application within 10 business days, then issues the permit or sends a list of items to fix. Your Zoning Clearance Certificate has to be in place before you can apply.
Will my Burlington lot need approvals beyond the City’s?
Some lots do. Inside the Niagara Escarpment Commission’s Area of Development Control, a new house needs an escarpment development permit unless it’s exempt, and the City’s building approvals come only after it’s granted, with no charge to apply. Lots in or next to watercourses, valleys, wetlands or the shoreline may need a Conservation Halton permit, which carries its own fees.
Definition Bank
| Term | Meaning |
|---|---|
| Service Index | The City’s rate per square metre for each type of building work |
| Floor area | Area measured to the outer face of exterior walls, excluding garages and unfinished basements |
| Pre-Building Approval | The City’s zoning, grading and tree review before a building permit |
| Zoning Clearance Certificate | Confirmation that plans meet zoning, needed before a permit application |
| Grading and Drainage Clearance Certificate | Approval of how water leaves the lot, needed before a permit issues |
| Forestry review | The tree check inside Pre-Building Approval when work affects trees |
| Development charge | A one-time charge on new homes that funds roads, water and other growth services |
| Front-ending Recovery Payment (FERP) | A Halton Region charge of $9,500 per single detached house, paid at permit |
| Education development charge | A school board charge per new dwelling unit, paid at permit |
| Occupancy permit | The City’s permission to move in, now required where development charges are deferred |
| Conditional permit | A permit that lets work start before every approval is in place, for an extra 20% |
| Minor variance | A Committee of Adjustment approval for a small departure from zoning |
| Committee of Adjustment | The City body that decides minor variances under the Planning Act |
| Demolition credit | A development charge credit when a building is replaced on the same land |
Entity Cards
City of Burlington
| Property | Value |
|---|---|
| Permit fee | $23.18 per m² up to 300 m² total, $29.90 above, $377 minimum |
| Pre-permit review | Pre-Building Approval: zoning, grading, forestry |
| Review time | 10 business days for a complete application |
Halton Region
| Property | Value |
|---|---|
| Development charge | $79,880.67 urban, $41,368.50 rural, per single detached house |
| FERP | $9,500, paid at building permit |
| Timing | Main charges due before first occupancy |
Committee of Adjustment
| Property | Value |
|---|---|
| Decides | Minor variances under Planning Act section 45(1) |
| Fees | $1,145 or $6,865, deferral $725 |
Catlin
| Property | Value |
|---|---|
| Services | Custom homes, whole home renovations, home additions |
| Permit role | Reviews site and zoning, prepares permit drawings, manages approvals |
| Contact | 919 Fraser Dr #9, Burlington, 289-427-1092 |
Sources
- City of Burlington, Building Permit Fee Schedule: Schedule A, Classes of Permits and Permit Fees (PDF)
- City of Burlington, 2026 Pre-Building Approval Application Fees, effective January 1, 2026 (PDF)
- Halton Region, Development Charges (DCs) and Front-ending Recovery Payment (FERP), rates effective April 1, 2026
- City of Burlington, Development Charges Update Study and Amending By-law to Development Charges By-law 41-2024 (PDF)
- City of Burlington, 2026 Rates and Fees, Schedule A of the Rates and Fees By-law (PDF)
- Halton District School Board, Education Development Charges
- City of Burlington, 2026 Development Application Fees, effective January 1, 2026 (PDF)
- Ontario Ministry of Municipal Affairs and Housing, CodeNews Issue 373: New Occupancy Permit Requirements in the Building Code for Deferred Development Charges, November 3, 2025
- City of Burlington, Residential Renovations and Additions
- City of Burlington, staff report: Deferred development charges to occupancy
- City of Burlington, Region of Halton and Halton School Boards, Development Charges, effective June 1, 2025 (PDF)
- City of Burlington, Applying for a Building Permit
- City of Burlington, Grading and Drainage Clearance Certificates
- City of Burlington, Home Construction and Renovation
- City of Burlington, Committee of Adjustment agenda, May 6, 2026 (minor variance notices under Planning Act section 45(1))
- City of Burlington, Committee of Adjustment minor variance staff reports, October 8, 2025
- City of Burlington, Residential Zoning By-law 09-2026, Part 1: Administration, May 2026 consolidation (PDF)
- City of Burlington, Zoning Checklists, FAQs and Handouts for Low-Rise Residential Neighbourhoods, Zoning By-law 2020, revised May 2026 (PDF)
- Catlin, Custom Home Builder in Burlington (services, service areas and contact details in site header)
- Catlin, Custom Home Building in Burlington
- Niagara Escarpment Commission, Development Permit Applications
- Niagara Escarpment Commission, Frequently Asked Questions
- Conservation Halton, Permitting and Planning
- Conservation Halton, Permitting